LUS Projects
Updated as of February 19, 2024
LED Street Light Project
LUS is replacing existing 21,000 street lights with LED lights. The LED street light project will improve nighttime traffic visibility and roadway safety, reduce electric consumption, decrease maintenance costs, and create possibilities for “smart city” functions. The project is estimated to save the city $500,000 to $800,000 a year.
• Project cost – $8,750,000
• Start date – began April 2022, anticipate completion mid-2024
• Progress – View LED progress
Moss Street Substation
Construction of a 69/13.8kV substation capable of serving a large portion of the load on the north side of Lafayette to reduce load on existing Peck substation and allow future expansion in this area. Benefits will include increased reliability and reduced restoration times during outages and maintenance. Project was initiated and budgeted in 2005 with substation location acquired in 2015.
• Project cost – $5,500,000
• Start date – begin construction Winter 2023/2024, anticipate completion in 8 months
• Progress – pending award of contract
Northeast Transmission Line
As part of the Moss Street Substation project, transmission lines connecting to the new substation will supply power to the area through the new Moss Street Substation. Transmission route was finalized in 2020. Pole design is complete, awaiting final property purchases. Contract for construction will be awarded mid-2024.
• Start date – begin construction Summer 2024 – pending servitude acquisition, anticipate completion in 14 months
• Progress – 100% completion of design phase
Downtown Sewer Lift Station
LUS plans to construct a major sewer lift station and force main to provide additional sewer capacity for downtown and the surrounding areas as well as mitigate overflows. The lift station will supply additional sewer capacity to serve approximately 2,000 residential units.
• Project cost – $10,000,000
• Start date – Bid August 2024, anticipate completion of construction in January 2026
• Progress – 100% completion of design phase
Commission Boulevard Water Treatment Plant
The plant will be able to process 4 million gallons of water per day and will have a ground storage tank with 1 million gallons capacity. The plant implements an ultraviolet light system paired with a chlorine gas process for disinfection. Commission Blvd is the 1st plant in Louisiana to use a new technology of biological filtration paired with a green sand filtration process. The plant is currently online and supplying water to the system.
• Project cost – $12,119,000
• Start date – project began July 2021, plant began operation in April 2023
• Progress – 100% complete
South Wastewater Treatment Plant Sludge Handling
The expansion of the South Wastewater Treatment Plant will accommodate additional wastewater treatment to keep up with area growth. These pre-treatment units and associated facilities allow the plant to more efficiently route wastewater flows and to reduce sludge handling costs.
• Project cost – $8,482,000
• Start date – began April 2021, new treatment units began operation November 2022
• Progress – 100% complete
Ambassador Caffery Treatment Plant Headworks Rehabilitation
Project to repair, rehabilitate, and coat the deteriorated concrete headworks basin. The concrete has deteriorated in some parts due to hydrogen sulfide exposure. The basin is necessary for processing and treating wastewater. (This project is partially funded by an ARPA grant from the Water Sector Program.)
• Project cost – $497,000
• Start date – bid June 8, 2023, anticipate completion in September 2024
• Progress – 8% complete
Elan Lift Station
Installation of a new sewer lift station at Elan Subdivision (E. Broussard Rd and Kaliste Saloom Rd). The lift station and force main will replace an existing community treatment plant serving the residential subdivision and school. The force main will discharge to a new LUS large gravity sewer on Kaliste Saloom Rd for final disposition at Ambassador Caffery Wastewater Treatment Plant. (This project is partially funded by an ARPA grant from the Water Sector Program.)
• Project cost – $1,626,925
• Start date – Bid June 29, 2023, anticipate completion in May 2024
• Progress – 85% complete